Federal Office for Civil Protection, SPIEZ LABORATORY
DDPS SAFETY LABORATORY PROJECT (SiLab)
Milestones
1996 |
Project proposal |
|---|---|
1999 |
Visit to BSL4 laboratory in Canada |
2001 |
Site chosen by the national defence directorate. Following an in-depth and thorough appraisal procedure, Spiez is selected as the site for the new SiLab |
2002 |
Feasibility study on the planned Spiez site |
2003 |
Political backing from the DDPS directorate. In view of departmental restructuring and the additional demands which the building of the SiLab would generate, the construction plans were presented to the directorate. It agreed that the project should continue as planned. |
2003 |
Establishment of project specifications |
2004/2005 |
Draft project phase with final documentation |
2005/2006 |
Construction project phase with final documentation |
2005/2006 |
Project submission - planning approval for military structures (MPV) Main environmental safety inspection – Real Estate Bill |
2006 |
Submission of the Military Real Estate Bill on SiLab |
2006 |
Detailed planning and preparations for the implementation phase |
2006 |
Detailed engineering phase and preparation of construction documentation |
| 2006 | Parliamentary approval of the required funding during the reading of the 2007 DDPS Military Real Estate Bill |
2007/2008 |
Call for tenders |
Nov 2007 |
Ground-breaking ceremony and project launch |
From mid - 2009 |
Commissioning / validation |
From 2010 |
Fully operational SiLab |